- EMS ISD Bond Progress
- Central Office
-
October 24, 2022
-
September 19, 2022
-
August 22, 2022
-
July 25, 2022
-
June 20, 2022
-
May 23, 2022
-
April 25, 2022
-
March 2022
-
February 2022
-
January 2022
-
December 2021
-
November 2021
-
October 2021
-
September 2021
Pictured above at left is an aerial photo of the central administration building progress. Above center, the steel structure installation over the finance, superintendent and operations suites continues. Above right, concrete walls are progressing.
-
August 2021
Pictured above at left is the administration building's Conrete Masonry Unit, or CMU. Pictured above middle are the exterior walls of the administration building. Pictured above right, the is the entrance of the admin building's contruction area.
-
July 2021
Pictured above and at left is the CMU block being utilized to form up the walls on the lower level. Pictured below is rebar that is in place to pour the main entrance to the building.
-
June 2021
From left, the northing parking lot pour has completed. Eastern walls in the business area are being formed. -
April 2021
The photos above show the process of drilling, rebar placement and concrete filling.
-
March 2021
The parking lot is being excavated and soil relocated on site, and the the building site is being excavated and prepped for piers.
-
February 2021
Construction trailer has been set in place with electricity and data. The security, silt, and tree fencing are complete.