Central Office

  • July 2021 Update

    • The CMU block is being utilized to form up the walls on the lower level. Rebar is in place to pour the main entrance to the building. 

    June 2021 Update

    • The northern parking lot pour has been completed
    • Site work delayed due to rain
    • Eastern walls in the business area are being formed for future concrete pour

    April 2021 Update

    • Piers are in the process of being drilled. They are filled with rebar and concrete, and 180 of the 300-plus piers have been completed.

    March 2021 Update

    • The parking lot is being excavated and soil relocated on site.

    • The building site is being excavated and prepped for piers.

    February 2021 Update

    • Construction trailer has been set in place with electricity and data. The security, silt, and tree fencing are complete.

    December 2020 Update

    • Naming the general contractor is an action item for Board consideration at the December meeting.  

    November 2020 Update

    • Competitive sealed proposal has been released for bidding. Project will come to the Board for consideration in December for the naming of the general contractor. CSP is out for bid. A pre-construction meeting was held last week to answer questions about the project.

    October 2020 Update

    • The competitive Sealed proposal has been released for bidding. The project will come to the Board for consideration in December 2020 for the naming of the general contractor.

    September 2020 Update

    • Still in final review, competitive sealed proposal (CSP) will be recommended as the procurement method.

    August 2020 Update

    • Still in final review, competitive sealed proposal (CSP) will be recommended as the procurement method.

    July 2020 Update

    • Reviewing final finishes

    June 2020 Update

    • Site visit to pin the building corners down. Reviewing final finishes

     May 2020 Update

    • Continued design meetings. Projected construction will begin in Fall 2020.

    April 2020 Update

    • Continue design meetings. Projected construction will begin in Fall 2020.
  • July 2021

  • June 2021

  • April 2021

  • March 2021

  • February 2021